MB-335: Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert Part 2
Question #: 21
Topic #: 1
DRAG DROP
–
A skateboard manufacturer uses route operations to schedule resources and estimate units per hour. All products use the same sub assembly item and resource sanding process.
You observe an increase in the number of units a sanding belt resource can produce. The production schedule is now inaccurate due to the number of units the sanding belt line can produce. You must make a permanent change to the number of units the resource can produce for all future orders.
You need to adjust the process quantity on the route operation.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
No answers
Selected Answer: A
———————————————————————-
Question #: 22
Topic #: 1
HOTSPOT
–
A discrete manufacturer uses Dynamics 365 Supply Chain Management for time and attendance registrations on the shop floor.
Production worker A and production worker B clock in at 7 AM. They clock out at different times. Their work schedules are shown in the following table.
You need to determine how the current configuration will book the time.
What is logged in the system for each worker? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
No answers
Selected Answer: A
———————————————————————-
Question #: 23
Topic #: 1
A company implements Dynamics 365 Supply Chain Management.
Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company. You have the following requirements:
• Locate a warehouse at the subcontractor building.
• Support picking and shipping activity tracking.
• Associate costs of transporting materials between the locations in the cost of the finished product.
You need to modify the production flow.
Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
A. Create a resource and work cell resource group for the subcontractor.
B. Modify the overflow work operation and associate it with the subcontractor.
C. Create transfer activities and assign them to the subcontractor.
D. Modify the overflow work activity and assign it to the subcontractor.
E. Create a new production flow version.
Selected Answer: ACD
———————————————————————-
Question #: 24
Topic #: 1
DRAG DROP
–
A manufacturer sends wiring harnesses to a vendor to be soldered to a connector. You create the subcontracting process in the bill of materials (BOM) and route to account for the items sent to the vendor.
You need to set up a new item model group for the service item.
Which three actions should you perform? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
No answers
Selected Answer: A
———————————————————————-
Question #: 25
Topic #: 1
A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.
The company requires that employees register time against each machine on the shop floor.
You need to configure the system so that employees can register time.
Which two configurations must be set up? Each answer represents a partial solution.
NOTE: Each correct selection is worth one point.
A. time registration workers
B. registration workflow
C. machines as a resource
D. electronic timecard parameter
Selected Answer: AC
———————————————————————-
Question #: 26
Topic #: 1
DRAG DROP
–
A manufacturing company uses Dynamics 365 Supply Chain Management. The company operates three eight-hour shifts per day, Monday through Friday.
The company purchased equipment for a new process that cannot be performed with existing equipment. This specialized equipment performs only this unique task. The machinery must always be monitored and controlled by a worker.
The machine must be added to the existing production line and be ready as soon as possible. Future planned production orders must not overload the running maximums of the new machine.
You need to configure the system.
Which four actions must you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
No answers
Selected Answer: C
———————————————————————-
Question #: 27
Topic #: 1
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?
A. Navigate to the resource. Configure a calendar deviation to set the calendar to closed for the next two days.
B. Navigate to the calendar used for production and close the next two days.
C. Navigate to the resource. Change the calendar to closed on the resource.
D. Navigate to the resource group. Change the calendar to closed on the resource group.
Selected Answer: A
———————————————————————-
Question #: 28
Topic #: 1
DRAG DROP
–
A company is implementing Dynamics 365 Supply Chain Management. The company is a subcontractor that produces subassemblies for two major customers, CustomerA and CustomerB.
The company prioritizes CustomerA production orders to start on Mondays. The production orders may take several days to complete. CustomerB orders are produced throughout the week, after CustomerA orders are completed. Work in process (WIP) must be calculated and consolidated for CustomerA and CustomerB respectively on the financial reports.
You need to configure the production requirements.
What should you configure? To answer, drag the appropriate configurations to the correct requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
No answers
Selected Answer: C
———————————————————————-
Question #: 29
Topic #: 1
You are the lead product design manager at a Process manufacturing plant.
A formula that produces egg yolks as a by-product. This by-product is added back into inventory at standard cost and can be used in other production batches.
You need to select the by-product cost allocation.
Which cost allocation type should you use?
A. Per series
B. Percent
C. Recycled
D. Per quantity
Selected Answer: A
———————————————————————-
Question #: 30
Topic #: 1
HOTSPOT
–
A company that assembles packaging material uses Dynamics 365 Supply Chain Management.
The glue that is used in assembly has run out of stock and will not be back in stock as expected. Another adhesive must be substituted for the glue. This will affect orders in planning as well as production orders that have started.
You need to ensure that the substitute adhesive is used in production until the glue is back in stock.
Which configuration should you use for each requirement? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
No answers
Selected Answer: B
———————————————————————-
Question #: 31
Topic #: 1
HOTSPOT
–
A company implements Dynamics 365 Supply Chain Management.
You need to ensure that cost roll-ups and sales price calculations are configured for the scenario.
Which options should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
No answers
Selected Answer: A
———————————————————————-
Question #: 32
Topic #: 1
DRAG DROP
–
A company uses Process manufacturing.
Employees work a half day so that they can attend a company event. You have a rush order that must be completed that same day.
After reviewing the net requirements of the batch order, only 400 of the total quantity of 1400 units must be completed today. The production manager must retain the original batch number as the quantity of 400. The original batch number must appear on documentation for the customer.
You need to split the batch order into two orders.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
No answers
Selected Answer: C
———————————————————————-
Question #: 33
Topic #: 1
DRAG DROP
–
A company uses Asset management in Dynamics 365 Supply Chain Management. The company also uses Dynamics 365 Guides independently of the Dynamics 365 Supply Chain Management implementation.
Maintenance workers require a checklist template to complete work orders. A solution must help the workers through work order steps. The solution must use Dynamics 365 Guides with Dynamics 365 Supply Chain Management.
You need to integrate the solution.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
No answers
Selected Answer: A
———————————————————————-
Question #: 34
Topic #: 1
DRAG DROP
–
A company uses the asset management module in Dynamics 365 Supply Chain Management.
A machine on the shop floor is noisy and emitting an odd smell. The shop floor manager must alert the repair team that the asset might require a repair, or a series of repairs, by one or more specialized repair technicians. All repair records must tie back to the initial investigation record in case of a safety audit.
You need to create components to initiate the process of tracking the requests.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
No answers
Selected Answer: D
———————————————————————-
Question #: 35
Topic #: 1
HOTSPOT
–
A company uses Dynamics 365 Supply Chain Management.
The company wants to use the distributed hybrid topology model to alleviate performance issues at some of its distribution centers. The company has a manufacturing plant, PlantA, which resides at the same physical location as the company home office in Frankfurt, Germany.
The company has the following distribution locations:
• Distribution1 covers Scotland.
• Distribution2 covers Ireland.
• Distribution3 covers the United Kingdom.
• Distribution4 covers Belgium, Germany, and the Netherlands.
• Distribution5 covers the Shetland Islands.
All distribution warehouses use Dynamics 365 Supply Chain Management to receive and distribute goods from PlantA.
Warehouse personnel use the warehouse app to perform their job functions. Because of their proximity to each other, Distribution1, 2, and 3 are managed together and frequently transfer goods between each location.
Due to several connection issues with Dynamics 365 Supply Chain Management, the Shetland Islands location struggles to perform tasks.
The company must maintain as little of its own IT infrastructure as possible, especially in remote areas, but still support daily activities at all locations.
You need to recommend the appropriate topology configuration.
Which type of scaled unit should you use? To answer, select the appropriate options in the answer area.
No answers
Selected Answer: C
———————————————————————-
Question #: 36
Topic #: 1
A company uses Dynamics 365 Supply Chain Management for Process manufacturing.
You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.
You need to optimize the planned production orders.
What should you do?
A. In Planned orders, combine the production orders.
B. Rerun master planning. Select the dynamic plan with a coverage time fence of two weeks.
C. Firm the orders.
D. Rerun master planning. Select the static plan with a coverage time fence of two weeks.
Selected Answer: A
———————————————————————-
Question #: 37
Topic #: 1
A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.
Break times are paid. The cost of a break time must be charged at the pay rate of the job in progress when the break starts.
You need to configure the break times to charge against the job in progress.
Which two actions should you perform? Each answer presents a partial solution.
NOTE: Each correct selection is worth one point.
A. Set Production Order Cost Category to Yes.
B. Set Direct Payroll Cost Standard Time to Yes.
C. Set Direct Payroll Cost Standard Time to Allocate.
D. Set Production Order Cost Category to No.
E. Set Direct Payroll Cost Standard Time to No.
Selected Answer: A
———————————————————————-
Question #: 38
Topic #: 1
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.
The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient.
You need to ensure that the system is set up to support the manufacturing process.
Solution: Create a formula version for each concentration level.
Does the solution meet the goal?
A. Yes
B. No
Selected Answer: B
———————————————————————-
Question #: 39
Topic #: 1
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.
The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient.
You need to ensure that the system is set up to support the manufacturing process.
Solution: Set up the IngredientB formula line as a phantom BOM.
Does the solution meet the goal?
A. Yes
B. No
Selected Answer: B
———————————————————————-
Question #: 40
Topic #: 1
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.
The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient.
You need to ensure that the system is set up to support the manufacturing process.
Solution: Configure the catch weight of IngredientA to allow for the variances of the concentrations received from the different vendors.
Does the solution meet the goal?
A. Yes
B. No
Selected Answer: B