PMI-ACP: PMI Agile Certified Practitioner Part 2
Question #: 51
Topic #: 1
Why should a project team reduce the work in progress?
A. It indicates poor project quality
B. It represents team member’s utilization
C. It represents unrealized value
D. It shows that the project is behind schedule
Selected Answer: C
Question #: 52
Topic #: 1
During a review session, a customer representative is concerned that a story fails to satisfy the scope of work. However, the product owner declares that the scope of work is complete.
What should be done with this story?
A. Mark it as incomplete and prioritize it for the next sprint
B. Mark it as complete, since the product owner has the final say
C. Discard it and create a new story for the remaining scope of work
D. Mark it as complete, since the team completed the scope of work
Selected Answer: A
Question #: 53
Topic #: 1
Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met.
The team has been using a rolling wave planning approach so far on the project.
How should the agile practitioner explain to senior management the benefits of this approach?
A. It ensures a consistent level of detail is available in the project schedule
B. It prevents a wasteful build-up of requirements inventory that may never be processes
C. It provides a concrete definition of product scope, cost and duration
D. It allows the team to lock down the stories to be included in a release
Selected Answer: B
Question #: 54
Topic #: 1
A team member is stressed due to a heavy workload, while other team members have some slack in their schedules.
How should the team lead address this?
A. Inform management, and suggest that additional resources may be required
B. Discuss the issue with the team in the daily stand up meetings
C. Meet personally with the stressed team member to brainstorm ways to better manage their time
D. Begin tracking the stressed team member’s tasks in a separate backlog for additional analysis and reporting
Selected Answer: C
Question #: 55
Topic #: 1
A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because both project teams request clarification on the requirements and the overall priorities.
What should the agile project manager do?
A. Provide both project teams with the highest priority needs
B. Request the project team’s questions in writing prior to the next meeting
C. Facilitate a meeting with each team and the product owner to finds a solution
D. Provide both teams with each project’s documentation
Selected Answer: C
Question #: 56
Topic #: 1
A seven-member agile team’s composition varies considerably in age, gender, culture, personality type, and professional background.
When planning a team-building event, what type of interpersonal skills should the project leader use?
A. Networking
B. Social awareness
C. Communication
D. Leadership
Selected Answer: D
Question #: 57
Topic #: 1
Due to its complexity, a new team member struggles with developing a concise user story.
What advice should the agile practitioner give to assist with developing the story?
A. Hand the story over to a more experienced team member
B. Break the story up and focus on the most valuable parts
C. Discuss the story at the retrospective
D. Pick another story from the product backlog
Selected Answer: B
Question #: 58
Topic #: 1
Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.
What should the agile practitioner do?
A. Jointly meet with the team and product owner to discuss options and determine the end date
B. Announce that the team has exceeded the predicted velocity, and that the end date will be earlier than planned
C. Ask the product owner to include additional features in the product backlog, then re-plan subsequent iterations
D. Ask the team to decrease velocity to meet contractual obligations and document this decision
Selected Answer: A
Question #: 59
Topic #: 1
A team’s technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.
What should the scrum master do?
A. Tell the technical lead to do the testing
B. Facilitate an open and focused team discussion that reinforces team agreements
C. Ask the team manager to advise the technical lead that all tasks are important
D. Encourage the team to take ownership of the delivery
Selected Answer: B
Question #: 60
Topic #: 1
Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.
What should the product owner do next?
A. Obtain approval from the change control board to discontinue the component
B. Ask the team to continue developing the component
C. Ask the team to discontinue developing the component
D. Request the sponsor’s formal approval to discontinue the component
Selected Answer: C
Question #: 61
Topic #: 1
A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.
What should the team do?
A. Estimate only functional requirements that will impact product quality
B. Add team resources
C. Refer the issue tot eh product owner
D. Break non-functional requirements into those that can be delivered in the given sprint
Selected Answer: D
Question #: 62
Topic #: 1
A development team and product owner disagrees on a user story in the product backlog.
What should the agile practitioner do?
A. Have the development team follow the product owner’s direction
B. Openly challenge the product owner in the effort to poke holes in their approach
C. Facilitate a conversation about the user story between the development team and the product owner
D. Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner
Selected Answer: C
Question #: 63
Topic #: 1
During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points.
How should this be handled?
A. The story should be assigned eight story points as per the majority vote
B. The story should be added to the backlog and reassessed later
C. The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached
D. The decision for the number of story points should be made by the customer
Selected Answer: C
Question #: 64
Topic #: 1
A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge.
What should the agile practitioner do?
A. Select and implement collaboration tools to augment team interactions
B. Provide each geographical area with their own product owner and divide the work between the teams
C. Increase the number of requirements documents and ensure they are clearly communicated
D. After several sprints, calculate velocity based on primary team location and use secondary team as reserve
Selected Answer: A
Question #: 65
Topic #: 1
Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires exclusive and frequent information to complete its sprint goal.
What should the agile team do?
A. Create a central repository for information, and provide access to team B
B. Use an information board that will be visible to all passing through the workspace
C. Email all stakeholders with status updates
D. Provide team B with the information on an ג€as neededג€ basis
Selected Answer: A
Question #: 66
Topic #: 1
Chart Base on the burn down chart, what is the iteration’s status?
A. It trended ahead of scheduled and completed everything on time
B. It took more time than expected and had to be lengthened
C. It trended behind schedule and did not complete everything on time
D. It took less time than expected and had to be shortened
Selected Answer: A
Question #: 67
Topic #: 1
During planning sessions, an agile practitioner notices that some team members do not share common ideas.
What should the agile practitioner do?
A. Ask the team if they would like to adopt alternative techniques
B. Create a team norms document to set particular guidelines
C. Ask the scrum master to resolve the issue at the stand up meeting
D. Capture feedback during lessons learned at the end of the iteration
Selected Answer: A
Question #: 68
Topic #: 1
More details for a story are required before the upcoming sprint planning meeting.
What should the scrum master do?
A. Email the product owner requesting detailed story specifications and wait for a response
B. Gather the details from the team members before sprint planning
C. Schedule a story grooming session with the product owner before sprint planning
D. Conduct a planning poker session with the team
Selected Answer: C
Question #: 69
Topic #: 1
Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective.
What should the agile practitioner do?
A. Review established ground rules with the team
B. Ask team members specific questions to identify the cause
C. Encourage the team to continue working to maintain the iteration’s schedule
D. Meet with the product owner and stakeholders to discuss the issue
Selected Answer: A
Question #: 70
Topic #: 1
A company is considering developing a new, complex application that will require a large initial investment. However, if successful, the profit potential is high.
When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?
A. Calculated planned percent complete (PPC)
B. Many small minimally marketable features (MMFs)
C. Story points rather than cost estimates
D. Calculated earned value (EV)
Selected Answer: B
Question #: 71
Topic #: 1
While reviewing the sprint burn down during a stand up, the scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.
What should the scrum team do?
A. For upcoming sprints, have QA team members ensure that their respective skill sets are considered when accepting stories
B. Have QA team members with the appropriate skill sets spend extra to help the team succeed
C. Ensure that QA team members who lack the appropriate skill up for training within the next few weeks
D. Ask QA team members experienced with the new automation framework to cross-train the other QA members
Selected Answer: D
Question #: 72
Topic #: 1
An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.
What should the team member do?
A. Influence the customer
B. Mention the idea at the next retrospective
C. Show the customer how much time and money would be saved
D. Present the idea at the next ceremony attended by stakeholders to obtain their input
Selected Answer: D
Question #: 73
Topic #: 1
During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to efficiently complete its stories.
What should the team do?
A. Cross-train some members in the automation framework to broaden their capacity with that skill
B. Ask the product owner to add team members to boost this particular skill set
C. Send a member to automation framework training when funds are available
D. Avoid using test automation by swarming on the testing tasks and using manual testing
Selected Answer: A
Question #: 74
Topic #: 1
During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer.
How should the team resolve this?
A. Refer to the values of the agile framework and the team
B. Review the signed customer contract
C. Check the sprint priority list
D. Submit the problem to the product owner
Selected Answer: D
Question #: 75
Topic #: 1
A project team realizes that an important task on the iteration backlog will take more time than originally estimated.
What should the project team do?
A. Continue working on the task until it is completed
B. Remove the task owner from the project team
C. Add resources to reduce time to task completion
D. Stop working on the task and include it in the next iteration
Selected Answer: A
Question #: 76
Topic #: 1
An executive sponsor of a new scrum team actively attends scrum ceremonies.
How does this benefit the team?
A. It helps the team to focus on and meet sprint goals
B. It reminds the team about who sponsors the project
C. It provides high-level project updates to the sponsor
D. It helps to quickly resolve issues using the sponsor/s influence
Selected Answer: D
Question #: 77
Topic #: 1
A legal department representative contacts the scrum master because, while the project’s budget has been maintained, it has exceeded its original contracted time and scope.
What should the scrum master do?
A. Meet with the team to gain alignment with the legal department’s need to stay within the contracted time and scope
B. Work with the customer to narrow the scope
C. Share the project’s trajectory with the legal department
D. Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliveries
Selected Answer: C
Question #: 78
Topic #: 1
An agile project leader notices that the team’s velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses.
What can happen as a result?
A. The team will be unable to understand the iteration’s status
B. The team will be unable to judge the project design’s validity
C. The team cannot give accurate updates to management
D. Team collaboration cannot be measured effectively
Selected Answer: A
Question #: 79
Topic #: 1
A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated.
What should the Scrum Master do?
A. Point out that the team chose to work on other requirements to speed up the project
B. Ensure that the product owner reviews the contents of the information radiator
C. Ensure that the next sprint planning meeting reviews the satisfaction histogram
D. Point out that it is the responsibility of the product owner to clarify requirements
Selected Answer: B
Question #: 80
Topic #: 1
During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested.
What should the agile practitioner do?
A. Work with the agile team and product owner to agree on the definition of done
B. Ask the sponsor to determine whether the product is completed
C. Plan another review after the product has been tested
D. Add testing to the backlog, and have the product owner reprioritize
Selected Answer: A
Question #: 81
Topic #: 1
During a sprint review, the product owner identifies a required improvement for a feature’s user interface (UI) delivered during the sprint.
What should the product owner do next?
A. Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer
B. Create a user story for this new improvement and prioritize it for the next sprint
C. Document it as a requirement creep
D. Ask the team to take on additional story points to improve the UI
Selected Answer: A
Question #: 82
Topic #: 1
A company is moving into a new space and is determining the best configuration for offices. The management team is also considering moving to an agile process.
What should an agilest give?
A. Arrange the office space to allow co-location of development teams and centrally located information radiators
B. Isolate each development team to reduce all outside distractions
C. Ensure management understands the need for isolation to allow for concentration
D. Define the agile method the company will be using and implement the office configuration based upon that method
Selected Answer: A
Question #: 83
Topic #: 1
An agile team member identifies a potential problem within the project team.
How should the team’s coach react?
A. Document the problem, escalate to the project manager, and develop a solution for the team
B. Add the problem to the backlog and assign resolution to a future iteration
C. Instruct the team to try to solve the problem within the team
D. Perform root cause analysis and report the problem to the product owner
Selected Answer: C
Question #: 84
Topic #: 1
Stakeholders are displeased with the latest release of a product’s software. While most stakeholders attended every sprint review, they were otherwise largely uninvolved in the project.
What should the agile practitioner have done to ensure stakeholder satisfaction?
A. Communicated early and often, as outlined in the communications matrix
B. Ensured engagement among stakeholders and the product owner
C. Conducted additional stakeholder reviews and demos
D. Worked with the product owner to prioritize user stories
Selected Answer: B
Question #: 85
Topic #: 1
An agile project manager notices that the product manager manages team member’s day-to-day tasks in a way that distracts them from their core responsibilities.
In addition, the team believes that their questions on product backlog prioritization are not being answered on time.
What should the agile practitioner do?
A. Discuss and address this in the iteration retrospective
B. Let the product owner know it is the project manager’s responsibility to drive a ream’s tasks
C. Discuss the roles and responsibilities of the project team with the product owner
D. Ask the product owner to work extra hours to answer the team’s questions
Selected Answer: C
Question #: 86
Topic #: 1
An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager.
What should the scrum master do?
A. Dismiss the team member
B. Discuss the situation with the functional manager
C. Report the functional manager to the project sponsor
D. Demand that the functional manager respect the project charter
Selected Answer: B
Question #: 87
Topic #: 1
During a mature agile team’s planning meeting, a team member proposes a new framework that would considerably reduce implementation time. However, the team lacks the confidence to try the new framework.
To help the team gain confidence, what should the agile practitioner suggest?
A. Develop a spike
B. Create an Ishikawa diagram
C. Perform a pre-mortem analysis
D. Complete a variance and trend analysis
Selected Answer: A
Question #: 88
Topic #: 1
The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.
What must the agile practitioner do?
A. Add the new change request as a new user story in the product backlog for the upcoming iteration
B. Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value
C. Recommend cancelling the current iteration and plan the change request into the next iteration
D. Recommend that the product owner add this change request as a user story to the backlog for the current iteration
Selected Answer: B
Question #: 89
Topic #: 1
During a review session, an agile team presented done requirements to a group of stakeholders. Stakeholder feedback indicated that the done requirements failed to meet most pressing needs and provide value.
What should the team have done to prevent this?
A. Reprioritized requirements prior to committing to iteration work
B. Ensured that requirements remained stable during the iteration cycle
C. Had stakeholders focus on items created after the product backlog was initially built
D. Worked on features rather than a set of components
Selected Answer: A
Question #: 90
Topic #: 1
A member of a project’s development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work and to rely on outside specialists is impacting team velocity.
What should the agile team lead do?
A. Send the member to training
B. Ask the outside specialists if database administration is required from the team
C. Send one member to training only after asking the team if there is an issue with the current work flow
D. Wait until all members of the team can attend training
Selected Answer: C
Question #: 91
Topic #: 1
What role should a servant leader perform to reduce team distractions and improve progress toward project goals?
A. Managing: To ensure compliance with the project plan
B. Mentoring: To share their knowledge with the team
C. Controlling: To ensure compliance with the scope, budget, and schedule
D. Auditing: To ensure adherence to organizational compliance policies
Selected Answer: B
Question #: 92
Topic #: 1
During a retrospective meeting, a team develops a large list of initiatives. All will have a positive impact and improve team performance.
What should the agile coach do next?
A. Positively acknowledge the list and share it with management
B. Immediately have the team implement the initiatives
C. Help the team choose one or two initiatives for immediate implementation
D. Ask the team to choose and implement the most complex initiative
Selected Answer: C
Question #: 93
Topic #: 1
A product owner concludes that the majority of a project’s value can be delivered by completing only the first half of the prioritized backlog.
What should the product owner do next?
A. Remove the second half of the backlog, and communicate their decision in the next backlog grooming meeting
B. Reprioritize backlog items to future iterations
C. Work with the team to deploy the first half of the backlog to ensure that value is realized
D. Meet with project stakeholders to review backlog and determine if the scope should be adjusted
Selected Answer: D
Question #: 94
Topic #: 1
During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.
What should have been done to avoid this?
A. A comprehensive user story with all non-functional requirements should have been created
B. Non-functional requirements should have been added to the acceptance criteria
C. Non-functional requirements should have been added to the definition of done
D. A team review of the scope of work should have been conducted
Selected Answer: B
Question #: 95
Topic #: 1
Midway through a sprint, a scrum team member advises the team of a new requirement that may change the initial scope.
What should the team do?
A. Work on requirements that the product owner may have overlooked
B. Record the scope creep in the change management log
C. Add the new requirement to the product backlog
D. Ask the scrum master to secure additional time and resources
Selected Answer: C
Question #: 96
Topic #: 1
A product owner, new to the role, is very enthusiastic about an agile project with an energetic team.
What should be done first to ensure successful delivery of the product?
A. Hold a meeting with the team and the product owner to develop the team charter, working agreement, guiding principles, and product vision
B. Ask the product owner to create the project vision and charter, and then discuss the guiding principles with the team
C. Hold a meeting during which the team can present the project charter, high-level project plan, and team values to the product owner
D. Send the product owner to format product owner training where the product owner can learn how to create a product vision
Selected Answer: B
Question #: 97
Topic #: 1
During a current sprint, a team member asks permission from the scrum master to investigate an alternative design approach.
What should the scrum master do?
A. Discourage the team member from deviating from the plan and document the request during the retrospective
B. Encourage the team member to research the issue and present the findings during the retrospective
C. Discourage the team member from using experimentation/spikes unless it is fully developed and accounts for a variety of use cases
D. Encourage the team member to use experimentation/spikes for continuous improvement and help the team understand why it is important
Selected Answer: D
Question #: 98
Topic #: 1
The scrum master for a large project must provide an estimate of what can be delivered in six months.
What should the scrum master do?
A. Commit to a specific feature set for delivery
B. Explain that a commitment will be provided after planning
C. Have the team estimate in story points to commit to a specific set of features
D. Use the team’s historical velocity to calculate a range of features that can be delivered
Selected Answer: D
Question #: 99
Topic #: 1
A member of the development team is working on a prioritized non-functional requirement involving integrating with a 3rd party system. This integration has not been done before on the project.
What should the project leader suggest?
A. Develop and document a detailed architectural design, peer review with the development team, and implement/test
B. Develop the functional requirements of the solution first before any non-functional requirement, as they provide more customer value
C. Discuss the integration requirement with the product owner and negotiate it to be lower on the backlog to focus on the minimal marketable feature
D. Develop and test the implementation approach and demonstrate it at the next sprint review to collect feedback
Selected Answer: D
Question #: 100
Topic #: 1
During a retrospective, the agile practitioner discovers that a team member’s process improvement idea has worsened the outcome.
What should the agile practitioner do?
A. Commend the team on trying the idea, then encourage discussion regarding alternatives
B. Ask a manager to direct the team on fixing the process
C. Encourage the team to continue executing the idea to see if it improves
D. Privately speak with the team member to convey that their idea worsened the outcome
Selected Answer: A